Project Overview

At Noble Power Solutions, we specialise in delivering high-quality energy solutions.

Recently, we successfully commissioned two key substations at the Rye Park Wind Farm, which stretches over 40 km in New South Wales. This project features 66 of the largest wind turbines in Australia, each standing 180 metres tall. The total generation capacity of the wind farm is 396 MW, with each substation having a generation capacity of 72 MW and 324 MW, respectively.

Our involvement included:

  • Pre-Commissioning:
    • Protection Relay testing including overall logic, communication (IEC61850) and protection element testing for all Transmission Lines, Transformers, Bus Zones, Feeders, Incomers, and Reactive Plant.
    • 330 kV AIS and 33 kV AIS & GIS Switchgear Functional Testing, including circuit breaker timing tests and interlocking matrix verification.
    • Standalone, primary injection, and polarity testing of all Current and Voltage Transformers, plus 3-phase primary injection stability testing of step-up transformers and restricted earth fault elements.
    • Reactive Plant testing via frequency response analysis and RLC circuit measurements.
    • DC circuit commissioning including battery discharge testing.
    • Overall SCADA and control system site integration and testing. Including integration with turbines power plant control system.
  • Hot Commissioning:
    • Final energisation and verification of systems to ensure proper operation.
    • Performance testing of substations under load conditions.
    • Calibration and adjustment of equipment as required.
    • Final system checks and troubleshooting to address any issues.
    • Handover and documentation of all commissioning results and system performance.

This project highlights our commitment to advancing reliable renewable energy and demonstrates our expertise in managing critical components of large-scale energy infrastructure. We are proud to contribute to the success of the Rye Park Wind Farm and its role in sustainable energy generation.

Project Snapshot

Description:
Rye Park Wind Farm

Location:
Rye Park, NSW

When:
January 2023 – June 2023

Contracting Sector:
Private High Voltage Wind Farm

Helping our clients succeed.

Developing and nurturing strong relationships is the key to success.

Noble Power Solutions was established in 2016 offering more than 15 years experience of specialist testing, commissioning and electrical engineering services to the power generation, transmission, distribution and end user industries.

Our attention to detail, focus on safety and rare combination of experience, skills and capabilities is what we believe makes Noble Power Solutions stand out from the competition.

Our Culture

NOBLE Adjective—having or showing fine qualities or high moral principles.

More than just a name, noble goes to the core of our business. It is a value which resonates within all of us and drives us to be the best we can for ourselves and our clients.

Safety Centered

When it comes to working with electricity, the health and safety of our people is paramount.

Owing to our extensive knowledge of the works we do and depth of experience within the industries we service Noble Power Solutions has an impeccable zero injury or lost time safety and environmental track record.

Regions Serviced

From our base locations in Tasmania and Queensland we offer our services to all clients in all States and Territories with Australia.

With a unique business model which allows us to be dynamic and responsive, in many cases we can mobilise within 24 hours of a client request.

Noble Power Solutions has a fully Integrated Management System (IMS) certified as complying with the requirements of ISO9001:2015, ISO14001:2015, ISO45001:2016 and AS/NZS 4801:2001.

Certified System - Quality ISO 9001, Environment ISO 14001, Health & safety AS 4801