Project Overview
Huntingwood Substation for a data centre connection in Sydney
132/22kV Private Substation in Huntingwood, NSW, a dedicated connection to the clients Data Centre. The scope of work included:
- Primary High-Voltage Equipment Testing:
- Current transformers
- Voltage transformers
- Circuit breakers
- Disconnectors
- Power Transformers
- Secondary Systems Testing:
- Battery chargers
- DC systems
- Transformer protection
- Bus bar protection
- Incomer and feeder protection
- Utilised IEC61850 messaging between devices
The Huntingwood Substation project received the 2018 NECA NSW Excellence Award in the Large Industrial category. The National Electrical and Communications Association (NECA) is the peak industry body representing the electrical and communications contracting industry across Australia.
Helping our clients succeed.
Developing and nurturing strong relationships is the key to success.
Noble Power Solutions was established in 2016 offering more than 15 years experience of specialist testing, commissioning and electrical engineering services to the power generation, transmission, distribution and end user industries.
Our attention to detail, focus on safety and rare combination of experience, skills and capabilities is what we believe makes Noble Power Solutions stand out from the competition.
Noble Power Solutions has a fully Integrated Management System (IMS) certified as complying with the requirements of ISO9001:2015, ISO14001:2015, ISO45001:2016 and AS/NZS 4801:2001.